Subject: Land
Activity Updates
Effective: April 1,
2004
Expiration Date:Two (2) Years
Supersedes:Not
Applicable
Authority:
Capital Program Administration is
responsible for developing, implementing and updating guidelines and procedures
supporting delivery of Capital Projects as delegated by the Hillsborough County
Administrator. Please refer to Administrative Directive #CS-12.
Purpose:
To provide guidance for planning, tracking, updating and
documenting Land Acquisition activities (Land) within project schedules
in PIMS.
Guideline:
Land updates are a crucial component of many project
schedules. Roles and responsibilities associated with Land updates are
clarified as follows:
Project Manager Responsibilities
�
Overseeing the project process, ensuring project objectives are
being met, monitoring and reporting on project performance, recognizing and
reporting on non-performance, and initiating corrective action
�
Identifying projects that require Land and subsequently building
a Land element (schedule and cost) into the PIMS project
�
Establishing the Land requirements (via completing the “Real
Estate Department Request for Services Worksheet“)
�
Control of the PIMS project schedule and cost, including
predecessor/successor relationships, activity durations, relationship type
(finish to start, start to finish, finish to finish, etc), and activity
progress (based on input from the Project Team)
�
Knowing and communicating status of the Land phase of their
projects (based on interaction with the Real Estate Department)
�
Submitting Project Change Requests and/or budget amendments when
applicable (including those resulting from Land issues)
�
Fully utilizing their leadership, communication, and influencing
skills to ensure they receive monthly Land updates from the Real Estate
Department
�
Communicating performance of Real Estate staff in support of
their assigned projects
Real Estate Department Responsibilities
�
Direct control over Land
�
Advising the project manager of Land issues impacting the
established project scope, schedule, or costs
�
Monitoring, tracking, controlling, and updating Land,
including but not limited to the following activities:
o
Start/Actual Start
o
Duration
o
% Complete
o
Finish/Actual Finish
o
Cost Estimate
o
Notes (at their discretion)
�
Publishing a monthly Land status report, the content of
which will be used by the project manager for incorporation into their project
schedules
�
Supporting the project manager by providing timely and realistic input
on Land
�
When eminent domain is applicable, timely referring the Land
portion of the project to the County Attorney�s Office for handling (note
updates shall continue to be processed through the Real Estate Department based
on their communications with the County Attorney�s Office)
Absent input from the Real Estate Department, the project manager
shall exercise their best judgment and update Land accordingly. The project
manager MUST then enter a Land Note into the project schedule indicating the
source of the Land data and notify management of non-compliance. The
project manager shall also indicate in the Land Notes should they choose to
enter Land updates in the project schedule that are different than the
input received from the Real Estate Department.
Any conflicts, discrepancies, or communication issues shall first
be resolved by internal department management and then, if necessary, by the Capital
Project Oversight Committee (CPOC) at the request of the parties involved.
“Template“ Land Activities
Real Estate Acquisition Tracking (REAT) is the tool the Real
Estate Department uses to plan, execute, and control parcel acquisitions. REAT
therefore contains the details of the Land procurement process. Due to the
complex and diverse nature of parcel procurements, the Capital Improvement
Program (CIP) project�s Land Phase template may only contain the following
generic activities:
- Submission of “Request for Services Worksheet“
— a zero duration Start Milestone
- Land Acquisition — default duration 360 days
(may be adjusted)
- BOCC Award — a zero duration Finish Milestone
This template is for
guidance only. The project manager may refine the schedule in coordination
with the Real Estate Department.
Procedure:
The project manager shall initiate Land work for
their project by submitting a “Real Estate Department Request for Services
Worksheet“ to the Real Estate Acquisition Section. The project manager shall
verify that their request has initiated a Real Estate Department project by
accessing the applicable REAT project in PIMS and/or communicating directly
with the Land Acquisition Section Manager when necessary.
The suggested sequence of events is as follows:
|
#
|
Action
|
Role
|
|
1
|
Identify need for Land in the project schedule
|
Project Manager
|
|
2
|
Establish Land requirements
|
Project Manager
|
|
3
|
Submit the “Real Estate
Department Request for Services Worksheet“ to the Real Estate
Department (this milestone activity shall “kick-off“ the Land
phase of the project)
|
Project Manager
|
|
4
|
Develop the Land schedule in REAT (targeted for entry within 10 days of receipt of above request)
|
Land Acquisition Section Manager
|
|
5
|
Retrieve the “Land Acquisition Tasks“ report to assess
which projects need Land updates
|
Land Acquisition Section Manager
|
|
6
|
Retrieve the “Land Phase Schedule Update Form“ for the
projects that require Land updates
|
Land Acquisition Section Manager
|
|
7
|
Manually update the Land status of respective
projects
|
Land Acquisition Section Manager
|
|
8
|
Return hard copy update form to the project manager by their
requested date. (The date for this action shall be as mutually agreed
to by the parties to facilitate the monthly PIMS update)
|
Land Acquisition Section Manager
|
|
9
|
Incorporate the Land update into their project
scheduling considerations
|
Project Manager
|
|
10
|
Submit comprehensive project schedule update to their
scheduler for inclusion in the overall project�s monthly update
|
Project Manager
|
Note: The project manager may also rely on their
personal communications with the Real Estate Department to gather the necessary
data to update their schedules.
Summary of applicable forms/reports:
- Real Estate Department Request for Services Worksheet —
maintained and available from the Real Estate Department
- Land Acquisition Tasks — retrievable via Oracle Discoverer
- Land Phase Schedule Update Form — retrievable via Oracle
Discoverer
Approval Signature:
___________________________ __________
Stephan J.Cassidy Date
Capital Program Administrator
___________________________ __________
Eric R. Johnson Date
Director, Management & Budget Department