Subject: Definitions
Effective: September 30, 2003
Expiration Date: Two (2) Years
Supersedes: Not
Applicable
Authority:
Capital Program Administration is
responsible for developing, implementing and updating guidelines and procedures
supporting delivery of Capital Projects as delegated by the Hillsborough County
Administrator. Please refer to Administrative Directive #CS-12.
Purpose:
To provide clarification as to the definition of many terms
related to capital project management.
Guideline:
The definition of various terms related to the delivery of
Capital Projects is as follows:
q
Active Projects - Those projects approved for funding in
the current Capital Improvement Program (CIP) that have not achieved (Project Completion
Date).
q
Annual Operating and
Maintenance Cost Impact -
The anticipated annual additional recurring cost of operating and/or
maintaining a new and/or expanded facility or infrastructure once it goes in to
service. This includes the cost of additional personnel required to operate
and/or maintain the new facility or infrastructure.
q
Baselines - A historical snapshot of a project plan
that provides a target against which one can track a project's cost, schedule,
and performance. Baselines contain historical project information that can be
used to compare variances between current project status and previous
commitments.
q
Baseline Project Cost - The cost estimate to deliver a
Capital Project that is used for initial project authorization.
q
Baseline Project Schedule - is the time line estimate to
deliver a Capital Project that is used for initial project authorization. The
schedule shall include, at minimum, milestone dates for commencing and
completing; planning (when appropriate and as previously completed), project
development, design, land acquisition, construction, close-out, and procurement
activities.
q
Baseline Project Scope - is the identification and
description of the purpose, features, and functionality that is to be achieved
by the Capital Project. The Baseline Project Scope is that used for initial
project authorization.
q
Beneficial Occupancy — a contractual term that signifies the
legal right to occupy a building or facility. It is the status
of completion of a project or portion of a project which is sufficiently
complete to allow utilization for the purpose for which it was intended.
q
Capital Budget - The financial plan of capital project
expenditures for the fiscal year beginning October 1 and ending the following
September 30. It includes appropriations for the first year of the Capital
Improvement Program (CIP). It is adopted by the Board of County Commissioners
as a part of the annual County Budget.
q
Capital Improvement Program (CIP) - The financial plan of
approved Capital Projects, as defined below, including their timing and cost
over a six-year period in the first year of a biennial budget, and over a five
year period in the second year of a biennial budget. The CIP is designed to
meet Hillsborough County's infrastructure needs in a responsive and efficient manner.
q
Capital Need - recognition of a necessary future capital
improvement based on program, facility or industry standards, and/or levels of
service. A Capital Need differs from a Capital Project in that it has not been
approved and funded by the Board of County Commissioners in the CIP.
q
Capital Needs Initiation Request Form — The first step in
initiating a Capital Project. It is the “short“ form for documenting a request
to include a capital improvement need on the Capital Project Request List.
q
Capital Project Initiation Request Form - The “long“ form formal
proposal to establish a Capital Project in the Capital Improvement Program.
Successful initiation results in funding for a Capital Project. Completion of
this form is necessary before a project will be moved from the Capital Project
Request List to the proposed CIP.
q
Capital Project Request List - A list of potential
future capital projects. Also commonly referred to as the “Unfunded
List“ or “Unmet Needs List.“
q
Capital Project - as defined in the Board of County
Commissioner's Policy Section Number 03.02.02.00. A distinct capital asset or
an improvement to an existing capital asset that is included in the Capital
Improvement Program.
q
Capital Project Number - a designator for tracking capital
projects and Capital Need Requests. Such a number will allow for the
identification and tracking of the Capital Project in PIMS. The number shall
distinguish an adopted Capital Project within the Capital Improvement Program
from a Capital Need not yet adopted by the Board of County Commissioners.
q
Capital Project Oversight Committee — The
group responsible for final issue resolution regarding capital projects
and quarterly review of CIP Status. Consists of the Assistant County
Administrators from Community Services and Management Services, the
Directors of Support Departments (Management & Budget, Purchasing,
Real Estate, etc.), and affected Program Managers. The Committee meetings
shall be facilitated by the Capital Program Administrator.
q
Data Date — The last date when
progress was recorded and a schedule calculated on a project. It starts the
work period for future activities and represents the date from which the
schedule was reforecast. All activities in the schedule after the Data
Date are planned activities
For example, if the Data Date is September 30, that does
not necessarily mean that all data in the schedule was collected, updated, or
inputted as of September 30, it signifies the date that the
schedule was recalculated based on information collected during the
month.
q Final Completion - This signifies all construction is
complete on the project. It is a contractual term indicating that all
outstanding “punch list“ items have been resolved. This includes: all manuals
and drawings; all site work including demobilization and clean-up; all
equipment and facilities are functioning as required; all vendor training, testing, and start-up etc is complete; and all spare
parts, where applicable, are delivered.
q Fiscal Closeout - The absolute final or last activity related to complete administrative
closure of the project. This is post-Final Completion and includes all bills
being paid or reconciled. Administratively all items are closed on the
project. This includes notifying the Clerk�s office to fiscally closeout the
project and move the asset from work-in-progress to the fixed assets account.
Individual department fiscal representatives are responsible for assuring
proper fiscal closeout procedures are accomplished.
q
Groundbreaking - A ceremonial milestone representing an
event to publicly announce the beginning of construction for a project.
q Inactive Projects - Those projects in
the Capital Improvement Program (CIP) that have achieved “Project Finish“. And,
those CIP projects that have been officially cancelled. There is no further activity
on the project.
q On/Off Schedule (Late) - A project is deemed to be off schedule
if the projected “Project Completion Date“ lags behind the “BOCC
Promise/Commitment“ date (as published annually in the CIP) by one day, or
more.
q PIMS Categories — all work activities associated with a project shall be grouped into
one of the following possible phases:
- Planning
- Development
- Procurement for Design
- Design & Permitting
- Land Acquisition
- Procurement for Materials
- Procurement for Construction
- Construction
- Administrative Close-out
q
Planning Area - The formal neighborhood community areas
as defined by the office of Neighborhood Relations.
q
Preliminary Study - shall include any internal or external
study or analysis, be it informal or formal, such as a needs assessment, a
cost/benefit analysis, or a concurrency analysis conducted to determine if a
potential Capital Need is warranted. It may be used to determine its ranking
among other Capital Needs on the Capital Needs List. A Preliminary Study would
occur prior to inclusion of a capital improvement in the Capital Improvement
Program. Generally, the Preliminary Study is funded with Operating Funds. The
Preliminary Study may be an internal or external assessment of the Project
Scope, Cost Estimate, and Schedule.
q
Program - consists of a series of like capital projects
managed by one Program Manager. Beginning with the Capital Improvement Program
for Fiscal Year 2002, the Programs will include the following:
- Fire Services
- Government Facilities
- Library Services
- Parks Facilities
- Solid Waste
- Stormwater
- Transportation
- Water and Wastewater Utilities
q
Program Manager - is the respective Department Director
who is responsible for the delivery of projects from the initiation of a
Project in the Capital Improvement Program to its Fiscal Close-Out. The
Program Manager assigns the Project Manager
and Team Members.
q
Project Change Request
Form - The document that
shall be used to request a modification to the Project Scope, Cost, and/or
Schedule.
q
Project Completion Date - is the date, assigned at the
discretion of the Program Manager or their designated representative, at which
a project is considered operationally complete. It signifies that the approved
scope of work as identified in the Capital Improvement Program has reached
completion. It is the commitment date to which the project has been promised
to be delivered in the CIP book.
q
Project Development - is intended to provide documented
information necessary to determine the specific type, design, and location of
capital improvements. This study occurs after the Preliminary Study. Project
Development shall result in the Baseline Project Cost, Baseline Project
Schedule, and Baseline Project Scope. Generally, Project Development will be
funded as a part of the Capital Improvement Program.
q
Project Finish — the end of a project, in its entirety, through
Fiscal Close-out.
q
Project Information Management System (PIMS) - the
County�s official Project Management enterprise based computer software
planning tools utilized for documenting and reporting Project information.
q
Project Manager - The Hillsborough County staff individual
assigned by the Program Manager, or their representative, to manage the
delivery of a Capital Project from Project Start to Project Finish. The Project Manager is empowered to make
necessary decisions to successfully manage the project and ensure its successful
completion. This shall include performing the necessary communications throughout
the functional organization and with external contractors or consultants for
issue resolution, direction, and authority. The Project Manager�s
responsibilities include, but are not limited to:
�
Managing the day-to-day activities associated with delivering the project.
�
Ensuring current and accurate project scope, description, schedule
progress, cost estimates, and applicable notes are available for reporting
status.
�
Reviewing their projects in PIMS (both Primavera P3e and
Discoverer) to ensure the project status is current and accurate.
�
Coordinating with Support Departments to obtain all necessary
time lines and associated cost estimates for delivering and reporting on Capital
Projects.
�
Coordinating with the Communications
Department to determine appropriate points for public meetings and/or press
releases.
�
Collecting and distributing
all information relevant to the project�s activities, progress, and status;
including those activities performed by others such as land acquisition and
procurement.
q
Project Start - The initiation of the project;
signifies the beginning of the first activity in the project schedule.
q
Project Team - A project team is comprised of the Project
Manager, the User Department/Agency, and related Support Departments such as
Purchasing, Real Estate, Management and Budget, County Attorney, and Debt
Management. The purpose of the Project Team is to involve the necessary staff
personnel with the needed skill sets throughout all phases of the project. The
Project Manager calls meetings of the Project Team to inform and resolve
issues. Each team member may not be required to attend each meeting, only
those where related information may be discussed. However, the Project Manager
will inform all members of issues and action resulting from each meeting. Issues
that cannot be resolved by the Project Team will be deferred to the Program
Manager. The Project Team is the group of participants in a project who are
directly involved in project management activities in support of the Project Manager.
The team concept is to create the group of people who will be responsible
during the various phases of project for keeping the scope, schedule and costs
within Board approved parameters. Their function is to support the Project
Manager and help identify and resolve problems
as the project proceeds. It is a collaborative approach to solving specific
issues. Project teams are needed because no one project manager, team
leader, director or even assistant county administrator has authority over all
of the county employees who are needed to deliver a County project. The team convenes,
under the leadership of the Project Manager, to resolve and address project
scope, schedule, or budget revisions.
q
Ribbon Cutting - A ceremonial milestone representing an
event to publicly announce the opening or operation of a project.
q
�Rolling 12-month look ahead“ - a review of the “Active“
projects already started as well those that will start in the next 12 months.
q “Schedule“
- The Primavera P3e term for the process of calculating a project schedule.
q Schedule Percent (%) Complete - Percentage of the project schedule
completed based on the duration of the actual progress compared to the planned
progress of the �Project Completion Date.“
q Substantially
Complete — The project may be used for its intended purpose. A contractual term indicating all work necessary
for the safe, proper, and total utilization and operation of the project for
its intended purpose is complete. This is prior to the “punch-list“ of
outstanding items being completed.
q
Support Department - Any department or office that is
responsible for providing the necessary internal services and/or relevant
information for the delivery of Capital Projects (i.e. Debt Management,
Management and Budget, Purchasing Department, Communications Department, Real
Estate and the County Attorney's Office).
q Total Budgeted Cost - Total approved estimated cost of the project
(all years, all sources, and all activities).
q
Total Project Actual Cost - Total actual cost at closeout of the project (all years, all sources, and
all activities).
q
Transfer to User Agency — the formal process of notifying
the intended user of a project’s completion and transferring responsibility for
operation and maintenance of the facility or asset to the User Agency.
q
User Agency/Department - The User Agency/Department may be
a County department or an outside agency that will be the ultimate
user/occupier of a facility or improvement; or the agency responsible for the
maintenance of the facility.
Procedure:
Not Applicable
Approval Signature:
___________________________ __________
Stephan J. Cassidy Date
Capital Program Administrator
___________________________ __________
Eric R. Johnson Date
Director, Management & Budget Department