Authority:
Capital Program Administration is
responsible for developing, implementing and updating guidelines and procedures
supporting delivery of Capital Projects as delegated by the Hillsborough County
Administrator. Please refer to Administrative Directive #CS-12.
Purpose:
To provide clarification as to the frequency of project
schedule updates.
Guideline:
Project schedules shall be updated, at a minimum, on a
monthly basis.
The update shall be effective on the last day of each
month. Departments may internally manage their update cycle in any manner they
deem appropriate to be in a position to "Schedule" their complete program
of projects with a new “Data Date“ as of the last business day of the month.
In this manner if the current month is June (regardless of
the actual day of the month), all projects in P3e shall have a data date no
earlier than May 31.
At the discretion of Departments; projects may be updated
and “scheduled“ more frequently with data dates between the last business day
of the previous month and the current date in order to capture more current
“real-time“ data.
Historical projects stored as “Inactive“ in P3e are excluded
from this policy.
Procedure: Not Applicable
Approval Signature:
___________________________ __________
Stephan J. Cassidy Date
Capital Program Administrator
___________________________ __________
Eric R. Johnson Date
Director, Management & Budget Department